SCHEDULED POWER INTERRUPTIONS

December 9 2018

11.17.18

11.11.18_Power Interruption Notice

October 27, 2018

October 20, 2018

43828515_2068215063491692_6010779251551240192_n

 

 

 

 

 

October 6, 2018

 

 

 

 

 

 

INTERRUPTION NOTICE 09-25-2018

 

 

 

 

 

Interruption 09-23-2018

 

 

 

 

 

 

 

 

 

INTERRUPTION NOTICE 09-07-18

INTERRUPTION NOTICE 08-31-18

 

 

 

 

UNSCHEDULED POWER INTERRUPTIONS

TO ALL OUR VALUED MEMBER-CONSUMER OWNERS.

Please be informed that the UNSCHEDULED Power Interruption that we are experiencing today, November 17, 2018, started at 5:00pm was due to a technical problem occured along the power line from Sugbongcogon to Kinoguitan.

Affected Areas: (Roadside Area)
Part of Talisayan
Part of Balingoan
Part of Kinoguitan

Our technical team is currently on foot patrol to locate the power line fault. Power will be restored immediately upon completion of all works and repairs.

Hoping for your understanding.

God Bless us all.

TO OUR VALUED MEMBER CONSUMER OWNERS

Please be informed that the power interruption we are currently experiencing since 4:30 in the afternoon, Oct. 14, 2018, is due to the explosion of some of our backbone line cut-out in Brgy. Agay-ayan, Gingoog City, brgy. mahayahay, cabug, Medina, brgy. Dangoan and Duka, Medina, due to the thunderstorm and lightning we experienced earlier. Another incident also happened in Brgy. Portulin near Brgy. Highschool, a fallen tree branch struck into our lateral line and caused tripping of our Agay-ayan, Substation. Our technical crew are now on works to restore the interrupted power line the soonest possible time, however, as of the moment we ask your apology for the inconvenience brought about by this incidents.

Thank you for your cooperation.

TO OUR VALUED MEMBER CONSUMER OWNERS

Please be informed that the power interruption we experienced last night October 7, 2018 at 11:40 in the evening was due to the toppled Mangium Tree which struck our power line at Barangay 24A Balanok, Gingoog City.

Affected Areas: Brgy. Talisay to Brgy. Lunao, Gingoog City

Power Restored: 1:11am

Our apology for the inconvenience.

Thank you for your cooperation.

(See photos below)

TO OUR VALUED MEMBER CONSUMER OWNERS

Please be informed that the power interruption we experienced today October 5, 2018 at 5:26 pm is due to the line to ground fault that occured in Jasaan – Kinoguitan NGCP 69 kv transmission line. However, please be informed that our technical team are already dispatched to repair the said line. Thank you.

TO OUR VALUED MEMBER CONSUMER OWNERS:

Please be informed that we will have a one (1) hour power interruption today September 25, 2018 @ 9:00AM – 10:00AM to facilitate the installation of cut-out assembly due to the damaged equipment in Portulin Distribution Line. Affected areas are Barangay Portulin, Tup-on, Gasa, Mandahilag and Pahindong. Thank you.

TO OUR VALUED MEMBER CONSUMER OWNERS

Please be informed that the POWER INTERRUPTION we experienced today September 24, 2018 is due to the line to ground fault that occurred in NGCP 69kV transmission line. Affected areas are from Claveria, some parts of Jasaan and Balingasag down to Talisayan. Further, please be informed that our crews are already dispatched and are currently working on to repair the said line. Target of power restoration is yet to be determined. Thank you.


 

TO OUR VALUED MEMBER CONSUMER OWNERS SERVED BY OUR GINGOOG 10MVA SUBSTATION:

Please be informed that the UNSCHEDULED POWER INTERRUPTION we experienced at twice this morning September 22, 2018 was due to our backbone line that was hit by a falling tree branch caused by pruning activity of Road Edge Construction located in Paz Village, Gingoog City.
(pls. see attached photos of the interrupted line)
Thank you.

42349706_2058531514460047_8258579922402934784_n 42373963_2058531604460038_7236199108329865216_n 42319635_2058531547793377_7375209568860635136_n 42314335_2058531627793369_7743029687621779456_n

 

 

 

 


TO OUR VALUED MEMBER CONSUMER OWNERS:

Please be informed that the UNSCHEDULED POWER INTERRUPTION we experienced last night September 21, 2018 at about 7:21 PM was due to tripping of our 69KV line because of a line to ground fault. Location of the line fault is in Artadi Hills, Artadi, Magsaysay just 8 km from the highway. We restored power using island mode via KEGI and is expected to make change power back to grid line at 8:00 am this morning, September 22, 2018.  Please be advised of a sudden power interruption for a maximum of 30 mins anytime now due to change of power.
(pls. see attached photos of the said interrupted line)
Thank you..

42414532_2058410444472154_2575012346275561472_n 42403053_2058410421138823_5835784099020668928_n42328981_2058410497805482_7900530802700582912_n

 

 

 


TO OUR VALUED MEMBER CONSUMER OWNERS:

Please be informed that the UNSCHEDULED POWER INTERRUPTION we experience today September 14, 2018 as of 9:00am is caused by the severed primary conductor of our power Feeder 2 line in Barangay 22, Citi Hardware, Gingoog City. Our personnel are already dispatched to repair the said line. (See photos below) Target of power restoration is yet to be determined.

41658114_2053764721603393_206684791335026688_n 41663773_2053764674936731_8078254900141621248_n 41713984_2053764558270076_2906462759283589120_n

 

 

 


TO OUR VALUED MEMBER CONSUMER OWNERS:

Please be informed that the UNSCHEDULED POWER INTERRUPTION we experience today September 11, 2018 since 8:30am is due to the low clearance of our 69kV line from Looc, Salay to Mandahilag, Talisayan. However, please be informed that our personnel are already dispatched and are currently working on to repair the said line. Target of power restoration is yet to be determined.

Thank you.

 


TO OUR VALUED MEMBER CONSUMER OWNERS:

Please be informed that the UNSCHEDULED POWER INTERRUPTION we experience as of the moment, September 4, 2018 is due to a fallen branch of mango tree that transpired in Barangay 25, Gingoog City which affected and broke the conductor of our backbone three phase line.

Affected areas are entire Gingoog City, San Juan, Murallon, Tinulongan, Bakid Bakid, Lunao and Mimbuntong.

Further, please be informed that our crews are already dispatched and are working on to repair the said line. Target of power restoration is yet to be determined. Thank you.